Around 7.30 am - at the height of morning peak hours, Mumbai commuters were left shocked when a portion of the Gokhale Bridge ... Civic governance has collapsed. My thoughts are with the citizens ...
The closure of the Gokhale bridge has caused considerable ... Reconstruction efforts began on December 2, 2023, following a partial collapse of the bridge in 2018. Originally slated for completion ...
will enforce a major 4.5 hour block on the down slow lines from 12.15am to 4.45am on the intervening nights of Jan 19-20 and Jan 20-21 to carry out dismantling work of the Gokhale road overbridge ...
The collapse of two bridges within nine months ... in addition to the closure of several minor bridges (see box), the 1975-built Gokhale bridge, a key east-west suburban connector, was closed ...
Regarding the Andheri East-Western Railway Link, or Gopalkrishna Gokhale Bridge (Rail Overbridge), the second phase of the railway section has been completed. Bangar said that the BMC’s limited ...
The earlier deadline set for opening the bridge was April 2025. Gokhale bridge was shut in November 2022, after an inspection revealed that various elements, including RCC columns, tie beams ...
It said that Additional Municipal Commissioner (Projects), Abhijeet Bangar, visited several bridge construction sites including the Gopal Krishna Gokhale Bridge in Andheri, the Sion (Sewri ...
The BMC still has a chance to meet the deadline to complete the Gopal Krishna Gokhale Bridge work. If the civic body manages to complete the last pier on both approaches by mid-February then the ...